Unit 1 Nose Dead Space Recovery Project

Site activities are progressing well and without any Safety or Quality incidents to date. All damaged truss steelwork has been
removed and the replacement of buckstays is ongoing. The next key milestone is delivery of new truss steelwork which started
on the 15th of June in line with the main installation phase commencing. Whilst fabrication timeframes are challenging a just-intime delivery strategy and some resequencing of installation has allowed us to maintain schedule for completion by 12th August.

A further key milestone achieved ahead of schedule is the alignment of the deformed NDS floor. This required significant
temporary steel reinforcement to enable the floor weighing almost 30 T to be lifted 100 mm back into its original position.